Oct. 27, 2025, 10:12 a.m.

Borozen school near the front ordered shelters at double the price

(A school in Borozenka. PHOTO: DREAM)

In the Kherson region, a school ordered the construction of a new shelter at prices that were almost twice the market price. The previous contractor did not complete the work and did not return the advance of 15 million, which the court ordered to recover.

This was reported by Nashi Hroshi.

The Borozensky basic institution of complete general secondary education signed a contract with the Mainline Plus consortium for the construction of a shelter worth 68.22 million. Work to repair the shelter, which was damaged in 2022, began in September 2024.

At that time, Karat Finance LLC was awarded the contract for more than 68 million, but the contract was terminated in December due to non-fulfillment of obligations. Prior to that, the company received an advance payment, which it did not return and did not confirm its intended use. In September 2025, the court ordered the company to return 15 million and pay a 1.1 million hryvnia fine.

The aftermath of the attack on the school. PHOTO: DREAM

The new building is planned to be completed by the end of 2026 on the territory of the institution in the village of Borozenske. This year, it is planned to perform works worth UAH 40.57 million. The village is located 39 kilometers from the front line. The funding is provided by the EU through the Ukraine Facility program, and the contract price is fixed, without the risk of inflation.

An analysis of material prices showed a significant overstatement: A-III 12 mm rebar was ordered at UAH 63,999 per ton, while the average market price is UAH 32-34 thousand per ton. Sweetondale Microelast EPP 2.5 cost 243 UAH/sq m, while Epicenter's price was 118 UAH/sq m. Waterproofing Bipol EPP 2.5 was taken into account at UAH 277/sq. m, the market price is about UAH 133-154/sq. m. Concrete B30 was priced at UAH 8,641 per cubic meter, and delivery separately at UAH 1,913 per cubic meter; concrete is offered for half the price. The Konner&Söhnen KS 110-3BE diesel generator was ordered for UAH 1.48 million, while the market price is UAH 819 thousand. The total probable overpayment on materials and equipment exceeds 11 million.

The aftermath of the attack on the school. PHOTO: DREAM

The contract was awarded without competition - no one applied for an open tender. At the same time, the State Audit Service did not find any violations during the monitoring of the procurement.

The media noted that the director of the Borozenskyi OPPZSO is Liubov Hloba, the procurement commissioner is Dina Honcharova, and the head of the rural VA is Alyona Okhrimovska. The Mainline Plus Consortium was established in June 2025 in Ternopil. Its founders: Avtomagistral-Zakhid LLC (80% owned by Serhiy Yuzvishyn) and Valk Construction Company LLC (20% owned by Bohdan Tverdun). During the four months of its existence, the consortium received contracts worth UAH 217.14 million, most of them from the Kherson Children's Regional Hospital.

And according to an investigation by the Center for Public Investigations, the construction of a school shelter was ordered in Vysokopillia, Kherson region, without an auction. At the same time, hundreds of millions have already been spent on the construction of the shelter in this school, which was received by companies previously suspected of embezzling budget funds and associated with the deputy head of the Kherson Regional Military Administration.

Анна Бальчінос

You might also like:

Dec. 4, 2025

Kherson CHP plant shut down due to attacks: houses are without heat supply

Director of dolphinarium arrested in Odesa for construction on Lanzheron

Corruption in the construction of school shelters exposed in Mykolaiv

Russian attack claims lives of 6-year-old child and three people in Kherson region

Dec. 3, 2025

Construction of water intake from the Southern Bug in Mykolaiv entrusted to a company with a history of corruption

Court blocks 200 million of ex-Crimea MP Novinsky's funds

Kherson Regional State Administration Failed to Comply with the Law on Open Budget Data

Occupants shell trolleybus depot and hospital in Kherson

American filmmaker launches global campaign to protect Kherson

Assistant Director General of South Ukrainian NPP caught in embezzlement

Dec. 2, 2025

Pensioners were discharged from hospitals in the temporarily occupied Kherson region ahead of schedule

Dec. 1, 2025

Ukrenergo announces tenders for design of transmission lines in Kherson region and two regions of the South

Gas supply contract in frontline village of Kherson region awarded to defendant in embezzlement case

Prosecutor's Office serves suspicion notice to FSB officer for torturing civilian in Kherson region