Nov. 15, 2025, 3:26 p.m.

Embezzlement of funds for the repair of a high-rise building revealed in Mykolaiv

(Misappropriation of funds. PHOTO: juresprudency.com.ua)

In Mykolaiv, possible corruption during the repair of a high-rise building was exposed. The court ordered a re-examination due to conflicting data on the cost of the work performed.

This is evidenced by the ruling of the Zavodskyi District Court of Mykolaiv.

A judge in Mykolaiv has ordered a repeat construction and technical expertise in the criminal proceedings against the director of Budtechnologiya-MK. He is accused of misappropriation of budget funds and forgery.

According to the investigation, the company carried out major repairs to the roof of a multi-storey residential building in Mykolaiv under a contract concluded in December 2020 with the Department of Housing and Communal Services of the City Council. The total amount of the contract was over UAH 607 thousand.

Investigators insisted that the contractor had entered false information about the scope and cost of work in official documents (an acceptance certificate and a certificate of value for May 2021). The data did not correspond to reality: the real cost of the work performed was no more than UAH 560,681, which means that the state suffered material damage in the amount of more than UAH 47 thousand.

Payment under the contract was made in June 2021 to the contractor's account. During the pre-trial investigation, it was found that the actual work performed and its accounting in the documents did not match, which led to conflicting expert opinions:

Due to these significant discrepancies, the prosecutor requested a second expert examination. The court partially granted the motion and ordered the experts of the Odesa Scientific Research Institute of Forensic Expertise of the Ministry of Justice of Ukraine to conduct the examination. The experts were warned of criminal liability for improper performance of their duties.

During the court hearing, the defendant pleaded not guilty and considered the appointment of a comprehensive examination inappropriate. The defendant's defense counsel objected to the re-examination, arguing that the previous findings were adequate evidence and that there were no contradictions in the experts' conclusions.

The proceedings were suspended pending the re-examination of the construction and technical expertise. The court ruling is final and not subject to appeal.

The court also recently seized the apartment and three cars of the director of the Graal utility company in Pivdenoukrainsk. He is suspected of misappropriating budget funds through fictitious procurement for the city.

Анна Бальчінос

You might also like:

Dec. 4, 2025

Director of dolphinarium arrested in Odesa for construction on Lanzheron

Corruption in the construction of school shelters exposed in Mykolaiv

Dec. 3, 2025

Construction of water intake from the Southern Bug in Mykolaiv entrusted to a company with a history of corruption

Court blocks 200 million of ex-Crimea MP Novinsky's funds

Mykolaiv allocated 83 million for modernization of heat supply

Court refuses to suspend head of Kutsurub community Inna Kopiyka

Assistant Director General of South Ukrainian NPP caught in embezzlement

Dec. 2, 2025

Head of Mykolaiv City Council's enterprise suspected of embezzling 700 thousand

Dec. 1, 2025

A dream in the South: checking out green energy projects in the southern regions

Ukrenergo announces tenders for design of transmission lines in Kherson region and two regions of the South

Prosecutor's Office serves suspicion notice to FSB officer for torturing civilian in Kherson region

Mykolaiv region plans to restore lyceum damaged by occupants

Mykolaiv pensioner corresponded with Russian special services

Nov. 30, 2025

Odesa karateka Terliuga dedicates World Championship bronze to her family

Support for communities in southern Ukraine discussed in Odesa