Feb. 21, 2025, 1:21 p.m.

Chornomorsk Lyceum Shelter Tender Raises Concerns Over Material Costs

(Photo collage: Intent)

An agreement was signed in Chornomorsk, Odesa Oblast, to build a shelter for Lyceum No. 3, but the tender raised questions about the cost of materials. The winner was Premiumstandardbud Construction Firm LLC with a contract worth UAH 97.8 million. A competitor who offered a lower price was rejected due to non-compliance with the requirements.

According to the Dozorro monitoring portal, the funds will be used to build a shelter for 333 people at 10-A Parkova Street in Chornomorsk. It will consist of two parts: the main building and a diesel power plant. A children's playground will be located above the protective structure.

Dozorro's experts found significant overpricing of construction materials, which could lead to an overpayment of UAH 10.2 million, which is 10% of the contract amount. For example, hot-rolled reinforcing steel is listed in the estimate at UAH 51,000-58,604 per ton, while the market price of this material from different suppliers ranges from UAH 30,515 to 38,390 per ton. Thus, the overpayment for this product alone could reach UAH 4 million. In addition, the contractor will supply concrete mix B25 [M350] at a price of UAH 5,280 per cubic meter, which is significantly higher than the offers of other companies, where this material costs from UAH 2,980 to UAH 3,340 per cubic meter.

The experts sent a request to the customer with calculations and a request to reconsider the prices for construction materials. However, a week later, they received a response that the contract price was confirmed by the project and the expert evaluation and was not subject to change.

On February 10, the State Audit Service began monitoring the procurement. It is worth noting that this procedure is the second attempt to conduct the procurement, as in September 2023, a similar tender was announced with an initial expected value of UAH 79 million. At that time, the proposal of High-Rise Construction Holding was rejected due to non-compliance with the technical requirements.

The development of the project documentation was carried out by individual entrepreneur Kyrylo Tsygankov for UAH 1.1 million, and its adjustment was carried out by individual entrepreneur Valentyn Yevdokymenko for UAH 80 thousand.

Premiumstandardbud Construction Firm LLC was founded in 2019 and is owned by Andrii Hlazkov, a resident of Odesa. The company started participating in public procurement only in the fall of 2023 and has already received contracts worth UAH 203 million.

Ірина Глухова

Також Вам може сподобатись:

March 15, 2026

The war should end this year, - artist Serhiy Anufriev

Head of State Forestry Agency from Odesa region pleads guilty in bribery case

Ukraine's first electric truck run goes to Odesa

Judge from Odesa region convicted without punishment for fraud is closer to release

Convicted Odesa judge Saltan complained that she was demanded to return 15 thousand dollars

Real estate at the address of an architectural monument in Odesa has fallen in price

Since the beginning of the year, Odesa City Hall has been offered four versions of the replacement for the Pushkin monument

Protective booms installed in the Dniester River in Odesa region

Odesa allocated 19 million for road repairs without auctions

Odesa court invalidates grain contracts worth 111 million at the suit of the tax authorities

March 14, 2026

Five hundred parking spaces near beaches have been developed in Odesa

National Bank plans to sell warehouses for UAH 96 million on April 1

Court finds actions of TCC in Odesa unlawful due to determination of husband as violator

The Tender Commission has finished accepting documents from potential concessionaires of the Chornomorsk port

Residents of Odesa and Luhansk regions convicted of high treason