Sept. 12, 2025, 8:42 a.m.

Funds were embezzled during the construction of the South Ukrainian NPP

(South Ukrainian NPP. PHOTO: nas.gov.ua)

A foreman of the South Ukrainian Nuclear Power Plant, who caused more than 5 million in losses to the state during the overhaul, will be tried in Mykolaiv region. He is accused of negligence and falsification of the scope of work and materials.

This was reported by the press service of the Mykolaiv Regional Prosecutor's Office.

Law enforcement officers sent an indictment to the court against a senior foreman of the repair and construction shop of the energy repair unit of the South Ukrainian NPP. He is accused of improper performance of official duties under Part 2 of Article 367 of the Criminal Code of Ukraine.

According to the investigation, the man had worked at the plant for many years and held the position of senior foreman of the repair and construction shop. In 2023, he was appointed responsible for quality control and scope of work during the overhaul of the waterproofing coating of the splash pool of power unit No. 3.

The investigation found that the official did not fulfill his duties properly. He controlled the scope of construction work and materials used by the contractor, but entered inaccurate information about the actual amount of materials and work in the acts of work performed.

In particular, the contractor declared more than 278 tons of one type of asphalt mix and almost 291 tons of another, while only 306 tons of one brand were actually used. The reports also indicated almost 50 tons of bitumen mastic, although half as much was actually used. A similar discrepancy was observed in the removal of sludge and construction waste: the declared volumes were significantly higher than the actual volumes.

As a result of these actions, PNPP unreasonably transferred more than UAH 5.7 million to the account of the contractor Resurstechnobud.

On August 19, 2025, the official was served a notice of suspicion under Part 2 of Article 367 of the Criminal Code of Ukraine - official negligence that caused grave consequences. He was chosen a measure of restraint in the form of house arrest at night. The accused faces imprisonment for up to five years with disqualification to hold certain positions or engage in certain activities for up to three years.

The overhaul of the waterproofing of the splash pool at the PSP cost over UAH 17 million. The contractor was aware of the tender and ensured the victory of his company, and after the contract was signed, he deliberately overstated the cost of materials and the scope of work.

Анна Бальчінос

Також Вам може сподобатись:

March 30, 2026

Cash in dollars and a car fleet without prices: Voznesensk mayor discloses income

Director of Municipal Enterprise in Mykolaiv pleads not guilty to embezzlement at school lunches

Salary, business and debts: How much did Pervomaisk Mayor Demchenko earn?

Diagnosis for $100: Voznesenskaya Hospital exposes a scheme to sell fake disability

March 29, 2026

From Copenhagen to Kharkiv: Where Kim was in 2025

Drone hits children: 13-year-old girl dies in Mykolaiv region

Transport fares to rise in Mykolaiv region from April 1

In Mykolaiv, 37 people killed in the RSA were honored: 4 years after the attack

Occupants unleash drone terror in the south: dozens of attacks, one killed and one wounded

March 28, 2026

Took advance payment and fled abroad: contractor taken into custody in Mykolaiv region

Ukrainian Armed Forces serviceman taken into custody for high treason in Mykolaiv

Millions down the drain: corruption investigation launched in Pivdenoukrainsk over restoration work

Deripaska, former owner of Mykolaiv plant, supports fundraising for the war in Russia

March 27, 2026

In Mykolaiv, a TCC employee was arrested for a scheme with the "Oberig" register

High treason or provocation: debate on ex-intelligence officer's case concluded in Mykolaiv