Bereg Trans Bud Secures ₴9.8M Contract for Radiation Shelter in Urozhayne Amid Controversy

(Photo: MOST)

Mykolaiv-based Bereg Trans Bud LLC, which was previously suspected of overcharging, will build a new radiation shelter in the village of Urozhayne, Beryslav district, Kherson region. Almost UAH 10 million was allocated from the local budget.

As it became known from the public procurement platform Prozorro, the contract was awarded without using the electronic procurement system and without holding an open tender.

It is about the construction of a dual-purpose facility with radiation shelter properties at 4A Myru Street. The work was ordered by the Executive Committee of the Beryslav City Council. On March 7, local authorities signed an agreement with Bereg Trans Bud from Mykolaiv, owned by Ruslan Bohlayov. He also owns four other construction companies.

The works are to be completed by June 30, 2025. The contractor will receive UAH 9.8 million for this.

The village of Urozhayne, which is part of the Beryslav community, is shelled almost daily by Russian troops located on the left bank of the Kherson region. Due to constant attacks, there are almost no surviving buildings in the village, but people still live there. Before the start of the full-scale war, 96,000 people lived in the Beryslav district, but as of 2024, the number of residents had dropped to 37,776.

Earlier, the Center for Public Investigations indicated that on August 15, 2024, the utility company Vysokopilskyi Komunservis entered into an agreement with Bereg Trans Bud LLC for the overhaul of a part of the water supply network in the village of Vysokopillia, Beryslav district, Kherson region, for a total cost of UAH 26 million 890 thousand 451. The procurement took place without the use of the Prozorro electronic system. According to journalists' estimates, the price of the works was overstated by 1.5 times. The authorized person, Olga Seranova, justified her actions by saying that the municipal enterprise had previously held open tenders with specific requirements for these works, but no one applied for the tender, and the work had to be done. Therefore, it was decided to conclude an agreement without using the electronic public procurement system with Bereg Trans Bud LLC.

The Education Department of the Fontansky Village Council of Odesa District also held a procurement to select a company to pay for the reconstruction of the building of the Gnezdechko Nursery and Kindergarten. The work will be performed by Bereg Trans Bud LLC.

Андрій Колісніченко

You might also like:

Jan. 28, 2026

Kivalov Odesa Law Academy ordered media advertising from a regular contractor

Jan. 26, 2026

Salaries and energy security: how Kherson allocated the budget of the municipal economy department

Contractor is under investigation for embezzlement during renovation of perinatal center in Kherson

In Kherson, UNICEF-funded contracts went to companies with criminal records

A former portrait painter from Kakhovka became a mouthpiece of the enemy in Crimea

Russian doctor is suspected of supporting the occupation of Kherson region

Jan. 25, 2026

Odesa court sentences Kherson resident to 10 years for collaboration

A company with an abnormally cheap offer was chosen to maintain fire protection systems in schools in Odesa

Jan. 24, 2026

Richelieu Lyceum in Odesa chose a breadwinner for students without an auction

Ex-head of Kherson region's village community sentenced to life imprisonment

Kherson utilities received 100 million for roads, transport and traffic lights

Former Kherson prosecutor charged with high treason

The occupiers decided to build a sanatorium on Cape Ai-Yuri in Foros

The contract for the reconstruction of a kindergarten in Serhiivka was awarded to a company with a local history

Kherson city council deputy released from pre-trial detention center after being charged with high treason