Auditors found that the construction costs for a school shelter in the Mykolaiv region had been overstated

(Photo: Mykolaiv Regional State Administration)

During the construction of a shelter at a high school in the Mykolaiv region, irregularities amounting to more than 900,000 hryvnias were discovered

This was reported by the Southern Office of the State Audit Service in the Mykolaiv region.

Specialists conducted an audit of procurement at the Prybuzh Lyceum, which includes a gymnasium and an elementary school, for the period from April 2025 to April 2026.

According to the audit findings, violations totaling more than 900,000 hryvnias were identified and rectified during the audit itself, the office’s press service reported.

The main violations involved overstating the scope and cost of construction work during the construction of a radiation shelter.

According to the auditors, unnecessary materials and work totaling 768 thousand hryvnias were unjustifiably included in the certificates of completion.

In addition, certain tasks involving the priming of metal surfaces were unnecessarily duplicated, resulting in additional expenses of 132,000 hryvnias.

These violations also led to an unjustified increase in expenses for technical supervision services.

During the audit, the contractor rectified the identified violations without additional funding. Specifically, at its own expense, the contractor performed additional work and supplied equipment, including the installation of paving with patterned elements, metal door units, shower pans, and water tanks.

An administrative offense report was filed against the lyceum’s authorized representative for violations in the area of public procurement. The Voznesensk District Prosecutor’s Office was informed of the audit’s findings.

Meanwhile, in Mykolaiv, the Department of Housing and Communal Services decided to acquire its own shelter—it plans to spend over 16.6 million hryvnias from the city budget to renovate a basement into a protective structure.

Ірина Глухова

You may also like:

Sept. 7, 2026

Nearly 5 million was spent on stabilizing a landslide-prone slope in Odesa

Sept. 4, 2026

Kherson has allocated 400 million for the purchase of mobile shelters

Sept. 1, 2026

A company with no competitors was selected to renovate the swimming pools in Chornomorsk

Aug. 31, 2026

A new suspect has emerged in the case involving a cover-up at a kindergarten in Odesa

Aug. 30, 2026

The contract to repair five kilometers of road in the Mykolaiv region for half a billion was awarded to a company from Odesa

Almost all contracts for the reconstruction of hospitals in Odesa were awarded without competition

Aug. 28, 2026

Agricultural enterprises in the Mykolaiv region increased production by 30 percent

Housing construction in the Mykolaiv region has nearly doubled

Aug. 27, 2026

In the Mykolaiv region, nearly 94 percent of children will attend school in person or through a hybrid model

Officials from the Mykolaiv Capital Construction Department have been accused of colluding with a contractor

Aug. 24, 2026

A contractor with 50 lines of business could receive 54 million for shelters in Vysokopillia

Aug. 23, 2026

In the Mykolaiv region, residents of Vinnytsia were charged 129 million for road repairs

Aug. 22, 2026

A Day of Mourning for Those Killed in the Russian Attack Was Declared in Mykolaiv Oblast

Aug. 21, 2026

A company director in the Mykolaiv region was convicted of embezzlement in connection with road construction projects

A businessman from the Mykolaiv region has been charged with embezzlement and concealment