The contractor decided to make money and overestimated the cost of work performed in Kherson region

(PHOTOS: Kherson Regional State Administration)

During the reconstruction of a kindergarten in Kherson region, a contractor overestimated the cost of work and included in the certificates something that was not in the project. Law enforcement officials have filed a lawsuit to recover the damage caused to the community.

This was reported by the press service of the Kherson Regional Prosecutor's Office.

The Oleshky District Prosecutor's Office has secured the opening of proceedings in the Economic Court of Odesa Oblast against a contractor that caused damage to the local budget during the reconstruction of a kindergarten in the village of Muzykivka, Kherson district.

Back in 2018, the Muzykivka Village Council and the limited liability company entered into a number of contracts for construction work at the kindergarten. However, according to the results of forensic construction, technical and economic examinations, it turned out that the contractor not only overestimated the cost of the work, but also included items in the acts of completion that were not in the design and estimate documentation at all. Thus, the contractor unjustifiably received UAH 1.38 million from the budget. The prosecutor's office is demanding that these funds be returned to the budget through the court.

At the same time, criminal proceedings are underway against a technical supervision engineer accused of negligence. According to the investigation, in 2019-2020, the official failed to ensure proper control over the reconstruction and did not conduct the necessary inspections.

Nevertheless, he signed certificates of completion that did not correspond to the actual scope of work. As a result, more than a million hryvnias were unjustifiably paid from the local budget. The proceedings over this fact are already under consideration, and law enforcement officers are considering bringing the official to justice.

In May, the reconstruction of a kindergarten in the Bilozersky district of Kherson region also resulted in criminal proceedings against the director of the construction company. According to the investigation, in 2019-2020, she failed to control the scope and quality of work, and the acts she signed contained false information - some of the work was done only on paper.

Анна Бальчінос

You might also like:

Jan. 10, 2026

Without rules and specialists: how delays hampered the reconstruction of Posad-Pokrovsky

In Mykolaiv region, 100 million worth of goods disappeared from the company's warehouses

Reconstruction of the basement of a kindergarten in Kherson region was estimated at 135 million

Mykolaiv exposes scheme of conscript evasion through expert medical commissions

Former law enforcement officer convicted in Kherson for torture and collaboration

Jan. 9, 2026

SBU detains enemy agitator in Kherson

Healthcare in the occupied Kherson region is on the verge of collapse

Russian special service officer sentenced for torturing military in Kherson

Three people killed and children wounded in Kherson region due to enemy attack

Jan. 8, 2026

Million-dollar corruption scheme organized at Mykolaiv power grid repair

In Kherson region, occupants sabotaged exits to the water by breaking boats

Kherson sued after misappropriation of funds for museum restoration

Jan. 7, 2026

American philanthropist Howard Buffett visited Kherson

Director of the occupied Kherson library is suspected under three articles

UN responds to shooting of humanitarian aid queue in Kherson region