Jan. 4, 2025, 9:53 a.m.

Repair of Odesa boiler house pipe will cost more than planned

(Photo: Odesa City Council)

The reconstruction of the chimney of Odesa's Pivnichna-2 boiler house, which collapsed during bad weather, has risen in price by almost UAH 2.5 million.

This was reported by the Center for Public Investigations.

On January 2, the Odesa City Heat Supply Utility signed a contract with Inventum Ukraine on the Prozorro platform without a tender procedure.

Adjustments usually relate to additional costs that arise due to an increase in the scope of work or rising prices for materials. The contractor has to complete the work by February 28.

In August last year, the same company was awarded a contract for "Additional Works" for the same facility, with a total value of UAH 2.4 million.

In the summer, Odesa began reconstructing the pipe of the Severnaya-2 boiler house, which collapsed during a strong wind last year. According to Mayor Gennadiy Trukhanov, UNICEF allocated UAH 60 million for the repairs. The construction was planned to be completed by November 1, 2024. This was described in detail by the CPR in its article.

Inventum Ukraine was registered in 2009 in Sumy. The founders of the company are three people: Hlib Minenko, Zhanna Talats and Oleksandr Hnapovsky. This is not the first time the company has entered into budgetary agreements, having already signed contracts totaling almost UAH 385 million. In 2018, Inventum Ukraine LLC was involved in a criminal investigation into the possible misappropriation of funds during the restoration of the boiler unit at Sumy CHP for UAH 17.5 million. In addition, in 2016, the company's accountant was tried for tax evasion of more than UAH 620 thousand. She was released from criminal liability because she had paid everything at the time of the trial.

On the night of November 27, 2023, a chimney more than 100 meters high, which belonged to the Pivdenna-2 boiler house, collapsed in Odesa due to hurricane winds. The incident occurred during bad weather.

An expert examination conducted in January 2024 revealed that the chimney collapse was caused by the poor quality of construction work during its construction. The study showed heterogeneity in the concrete, with samples having different strengths depending on the site. The conclusion of the experts was unequivocal: it was impossible to restore this pipe, and a new structure had to be built.

Ірина Глухова

Також Вам може сподобатись:

April 1, 2026

Petition to protect architectural monument registered in Odesa

From a mansion to tens of thousands of dollars: what Odesa Deputy Mayor Filatov's declaration showed

Odesa: SBU detains Russian agent on explosion of heating equipment

Odesa authorities accused of sabotaging protection of historical monuments

In Odesa, a sailor was sent to a detention center for a scheme with formal service

March 31, 2026

Moldovan citizen convicted in Odesa for attempting to bribe detective

The mayor of Bolgrad earned 150 thousand more last year than in 2024

Cogeneration: a big failure of the Odesa authorities

Odesa customs inspector detained on suspicion of systematic extortion

Odesa Regional State Administration Wins a Court Case Against the Owner of a Monument on Frantsuzsky Boulevard

Myths about NMT and distance schools: what is true and what is not Реклама

Trukhanov has not yet filed a lawsuit against Zelensky over deprivation of citizenship

Man injured in Russian strike dies in Odesa

Boomer bear dies in Odesa zoo

The mayor of Izmail and his wife earned money last year by selling electricity