Repair of Odesa boiler house pipe will cost more than planned

(Photo: Odesa City Council)

The reconstruction of the chimney of Odesa's Pivnichna-2 boiler house, which collapsed during bad weather, has risen in price by almost UAH 2.5 million.

This was reported by the Center for Public Investigations.

On January 2, the Odesa City Heat Supply Utility signed a contract with Inventum Ukraine on the Prozorro platform without a tender procedure.

Adjustments usually relate to additional costs that arise due to an increase in the scope of work or rising prices for materials. The contractor has to complete the work by February 28.

In August last year, the same company was awarded a contract for "Additional Works" for the same facility, with a total value of UAH 2.4 million.

In the summer, Odesa began reconstructing the pipe of the Severnaya-2 boiler house, which collapsed during a strong wind last year. According to Mayor Gennadiy Trukhanov, UNICEF allocated UAH 60 million for the repairs. The construction was planned to be completed by November 1, 2024. This was described in detail by the CPR in its article.

Inventum Ukraine was registered in 2009 in Sumy. The founders of the company are three people: Hlib Minenko, Zhanna Talats and Oleksandr Hnapovsky. This is not the first time the company has entered into budgetary agreements, having already signed contracts totaling almost UAH 385 million. In 2018, Inventum Ukraine LLC was involved in a criminal investigation into the possible misappropriation of funds during the restoration of the boiler unit at Sumy CHP for UAH 17.5 million. In addition, in 2016, the company's accountant was tried for tax evasion of more than UAH 620 thousand. She was released from criminal liability because she had paid everything at the time of the trial.

On the night of November 27, 2023, a chimney more than 100 meters high, which belonged to the Pivdenna-2 boiler house, collapsed in Odesa due to hurricane winds. The incident occurred during bad weather.

An expert examination conducted in January 2024 revealed that the chimney collapse was caused by the poor quality of construction work during its construction. The study showed heterogeneity in the concrete, with samples having different strengths depending on the site. The conclusion of the experts was unequivocal: it was impossible to restore this pipe, and a new structure had to be built.

Ірина Глухова

Також Вам може сподобатись:

March 11, 2026

In Odesa port, BES disrupted a scheme to export corn to Malaysia for 202 million

Tenant acquires winery in Odesa region for 10 million

Renovation of a school canteen in Odesa region attracts law enforcement interest

Officials of village council in Odesa region sent to jail for extortion

The deputies expressed no confidence in the head of Podil district administration Lazarenko

Hundreds of millions and crime: what the reconstruction of a special school in Odesa has revealed

Odesa law enforcement exposes corruption in firewood procurement for the Armed Forces of Ukraine

Fortifications in Kherson region: the department buys construction materials worth millions

Odesa region exposes scheme of conscripts' escape to Transnistria

Apartments in Kyiv and hundreds of thousands in foreign currency: what the deputy head of Odesa Regional State Administration declared

Woman sentenced in Odesa region over the death of her baby

Night, fog and an attempt to escape across the Danube: a man prepared a wetsuit and a water scooter

Scheme to enroll students to avoid mobilization exposed in Odesa

March 10, 2026

Odesa starts collecting proposals for the development strategy implementation plan

Deputies of Podil District Council convened for a session due to dismissal of the head of the district administration