18 March 2025

Kherson Oblast Announces New ₴59.3M Tender for Home Repairs After Errors

(Photo: Photo: Yulia Ratsybarska/Radio Liberty)

The Kherson Oblast Restoration Service canceled one of the procurements for the repair of houses in Posad Pokrovsky and announced a new one, which is UAH 5 million more expensive.

According to the Center for Public Investigations, this became known from the announcement of the cancellation published on the public procurement website Prozorro.

The open bidding with specifics concerned the overhaul of houses on Zelena Street: Zelena (houses 13, 16, 33, 35, 40, 45), Pokrovska (houses 5, 11, 14, 22, 39, 40, 51, 54), Sportivna (houses 14, 15, 20) and Khersonska (houses 8, 23, 24, 32, 33, 37, 56, 62, 64, 71, 75, 82, 84, 93, 95, 97). The contractor had until December 31, 2025, to restore the roofs, repair the facades, install utilities, and equip the interior. The expected cost of the work was UAH 54.3 million.

The tender was to be held on March 17. However, three days before the auction, the Restoration Service discovered irregularities that could not be eliminated:

"The calculation of the expected cost of construction works contains technical errors that significantly affect the calculation and amount of the expected procurement cost," said authorized person Nadiia Funtova in the protocol.

So after a while, the Kherson Oblast Reconstruction Service announced a new tender, but the cost of reconstruction increased by UAH 5 million to UAH 59.3 million. The auction is scheduled for March 25.

Since the end of February, the Kherson Regional Reconstruction Service has started announcing tenders for the repair of houses damaged by Russians in Posad Pokrovsky. They announced five tenders for more than 238 million hryvnias to repair houses and two auctions for the construction of 103 residential buildings.

On March 7, 2025, the Government of Ukraine allocated 5.2 billion hryvnias for the comprehensive restoration of five settlements, including Posad Pokrovske in the Kherson region. The plan is to "rebuild better than it was," which means a comprehensive approach to modernizing infrastructure and improving the lives of citizens.

Олеся Ланцман

You may also like:

Aug. 19, 2026

The restoration service was unable to provide a cost estimate for the restoration of the Varvarivsky Bridge

A Russian soldier was taken into custody for attacking a house in Kherson

Residents of Vinnytsia outmaneuvered the Odessa lawmaker's company in the race for a 700-million tender

A propaganda story cost a forester from the Kherson region 15 years in prison

Only a company owned by a lawmaker submitted a bid for a 238-million road repair project in the Odesa region

Ukraine carried out a prisoner exchange; defenders from the Kherson region have returned home

In the Kherson region, a contractor and an engineer are on trial for fraud related to the repair of damaged buildings

Odessa has decided who will provide meals for schoolchildren at a cost of 302 million

In Kherson, Russians struck a minibus carrying passengers; there are casualties and injuries

The enemy struck an industrial facility in the Mykolaiv region with an X-22 missile

Aug. 18, 2026

A resident of the Kherson region fought against the Ukrainian Armed Forces as a member of "Storm-Z" and will stand trial

Madyar announced new European UAVs for the Kherson sector

A new company, with no competitors, was awarded a 15-million contract in the Kherson region using EU funds

The director of an agricultural company owned by Kherson Mayor Kolykhaev was convicted of aiding the Russian Federation

Aug. 17, 2026

In July, the occupiers destroyed more than 10,000 trees and plants in "Askania-Nova"