The court postponed the hearing of the Odessa Thermal Power Plant's appeal in the case involving 750,000 hryvnias until November

(PHOTO: usionline.com)

The Odesa Combined Heat and Power Plant is to be charged more than 750,000 hryvnias for electricity consumed in January–March 2021. The company disagreed with the court’s decision and filed an appeal, the hearing of which has been postponed until November. 

This is stated in a ruling by the Southwestern Commercial Court of Appeals.

The lawsuit against JSC “Odesa CHP” was filed by the state-owned enterprise “Ukrinterenergo.” In July, the Commercial Court of Odesa Oblast granted its claims and ordered the CHP to pay 750,517 hryvnias.

This amount consists of several parts:

The Odesa Thermal Power Plant asked the appellate court to overturn the decision and deny Ukrinterenergo’s claim. A final decision on the appeal has not yet been issued.

The hearing was originally scheduled for October 13, 2026. However, the hearing was postponed because the presiding judge will be on leave.

The appeal will now be heard on November 3, 2026, at the Southwestern Commercial Court of Appeals in Odesa. A representative of “Ukrinterenergo” will be able to participate in the hearing online.

As previously reported by Intent, the Odesa Thermal Power Plant filed a lawsuit against the municipal enterprise “Odesa City Heat Supply” to recover 3.18 billion hryvnias in debt.

Ірина Глухова

You may also like:

Nov. 19, 2026

Harry Gray: a native of Odessa, whose novel was adapted into the film "Once Upon a Time in America"

UNESCO condemned Russia's attacks on the historic center of Odesa

A bronze foundry in downtown Odessa has been put up for auction

An Odessa resident has registered more than 100 Starlink terminals for Russians

In Odesa, a former head of the Housing and Utilities Department awarded himself bonuses amounting to up to 300 percent of his salary