10 July 2025

The contractor decided to make money and overestimated the cost of work performed in Kherson region

(PHOTOS: Kherson Regional State Administration)

During the reconstruction of a kindergarten in Kherson region, a contractor overestimated the cost of work and included in the certificates something that was not in the project. Law enforcement officials have filed a lawsuit to recover the damage caused to the community.

This was reported by the press service of the Kherson Regional Prosecutor's Office.

The Oleshky District Prosecutor's Office has secured the opening of proceedings in the Economic Court of Odesa Oblast against a contractor that caused damage to the local budget during the reconstruction of a kindergarten in the village of Muzykivka, Kherson district.

Back in 2018, the Muzykivka Village Council and the limited liability company entered into a number of contracts for construction work at the kindergarten. However, according to the results of forensic construction, technical and economic examinations, it turned out that the contractor not only overestimated the cost of the work, but also included items in the acts of completion that were not in the design and estimate documentation at all. Thus, the contractor unjustifiably received UAH 1.38 million from the budget. The prosecutor's office is demanding that these funds be returned to the budget through the court.

At the same time, criminal proceedings are underway against a technical supervision engineer accused of negligence. According to the investigation, in 2019-2020, the official failed to ensure proper control over the reconstruction and did not conduct the necessary inspections.

Nevertheless, he signed certificates of completion that did not correspond to the actual scope of work. As a result, more than a million hryvnias were unjustifiably paid from the local budget. The proceedings over this fact are already under consideration, and law enforcement officers are considering bringing the official to justice.

In May, the reconstruction of a kindergarten in the Bilozersky district of Kherson region also resulted in criminal proceedings against the director of the construction company. According to the investigation, in 2019-2020, she failed to control the scope and quality of work, and the acts she signed contained false information - some of the work was done only on paper.

Анна Бальчінос

You may also like:

June 6, 2026

Currency at home and property under occupation: what the heads of Kherson medical institutions declared

Kherson reallocated 419 million to utilities

Kherson resident tortured and threatened to cut off his fingers: court sentences Russian policeman

Ecocide and the tragedy of thousands of people: three years after the explosion of the Kakhovka HPP

For telling the truth about Kherson and the war: American correspondent is awarded an order

June 5, 2026

Case on fictitious disability for 16 thousand dollars sent to court in Odesa

102 million for officials: Kherson MVA approves management budget for 2026

Agribusiness in the occupied Kherson region, Cyprus and a deputy from Odesa: SBU uncovers booking scheme

Head of a driving school from Kherson convicted for schemes with fake IDs

Ex-mayor of Kherson Saldo convicted for looting of bakery plant

June 4, 2026

High Council of Justice fails to dismiss judge from Odesa region in case of schemes for conscripts

Top savings of Mykolaiv hospital managers: who keeps millions

Millions for landscaping, water and fuel: what Odesa City Green Building Committee bought

Anti-drone nets, electronic warfare and mobile shelters: how Kherson is being protected

In Odesa, a contractor embezzled the budget for ventilation and heaters for a lyceum