Restoration of the Jewish Hospital in Odesa for an EU loan: journalists reveal inflated prices in the estimate

(Photo: google.maps)

In Odesa, the city council has chosen a contractor to restore the surgical pavilion of Hospital No. 1, known as the Jewish Hospital. The tender was attended by a single bidder, so the Capital Construction Department did not have to choose between the cheaper bidders.

As reported in the Prozzoro system, on September 13, the agreement was signed with Exterior Design LLC. The value of the contract for price adjustment is UAH 167 million 938 thousand.

The project involves large-scale works: repair of facades, interior decoration, installation of water supply, ventilation, heating, alarm systems, etc. The total cost of the work is financed by a loan from the European Investment Bank, and VAT is covered by the local budget.

Investigative journalists from the Nashi Hroshi publication found serious overestimates of prices for construction materials and equipment in the estimate. For example, rebar was priced at UAH 66,461 per ton, although its value on the market is two times lower. In particular, Metinvest-SMC LLC's online metal-roll store sells such rebar at UAH 29,110/t, while Odesa-based Zenit metalware offers it at UAH 33,400/t.

Prices for expanded polystyrene, curb stones and gas blocks are also overpriced, by 15-73% more than market prices.

BR 100.20.8 curb stones were priced at 299 UAH/unit. Recently, the Zaporizhzhia-based utility Eluash ordered them at 180 UAH/each, and the Kyiv-based utility Road Maintenance Department for the Repair and Maintenance of Roads and Facilities in Darnytsia District at 201 UAH/each, which is 33-40% cheaper, the investigators write.

In addition, a gas block measuring 150x200x600 was priced at UAH 4,709 per cubic meter. The online store "TBC Alex-Group" offers such aerated concrete at a wholesale price of UAH 3,210 per cubic meter, and "Epicenter" in Odesa offers such blocks at UAH 4,000 per cubic meter, which is 15-32% cheaper than in the estimate.

The indicated average salary of workers (UAH 13,708) was lower than the real average salary in construction in Odesa (UAH 23,000), which also raises questions about the transparency of the estimate.

Earlier, the reconstruction of Odesa Maternity Hospital No. 5, for which UAH 175 million was allocated, attracted the attention of journalists due to possible overpricing of construction materials and equipment. The project is being financed by a loan from the European Investment Bank, with VAT covered by the local budget.

Ірина Глухова

Також Вам може сподобатись:

March 12, 2026

Odesa denied request to cancel arrest of maritime college property for abuse

Diagnosis for 16 thousand dollars: family doctor detained in Odesa for abuse

Modernization of canteens of two schools planned in Odesa region

Property of gas station chain seized in Odesa region for fuel production

Odesa raises fees for using public restrooms

Odesa plans to improve the embankment from Lanzheron to the Golden Beach

Chief of Staff of Odesa Regional State Administration Zavadskyi declared a 400-meter house

Civil servants of Odesa region administrations received lower salaries

Odesa Executive Committee considers financial assistance and housing for IDPs

Vasyl Skromnyi, actor from The Adventures of Elektronik, passes away in Odesa

Police officer arrested in Odesa for misappropriation of funds for treatment

March 11, 2026

In Odesa port, BES disrupted a scheme to export corn to Malaysia for 202 million

Tenant acquires winery in Odesa region for 10 million

Renovation of a school canteen in Odesa region attracts law enforcement interest

Officials of village council in Odesa region sent to jail for extortion