Sept. 24, 2024, 11:01 a.m.

Mykolaiv fails to deal with coastal protection

(Photo: Wikipedia)

In Mykolaiv, another tender for coastal protection works in the Velyka Korenyha neighborhood of the city's Zavodskyi district failed. It was planned to spend UAH 1 million 670 thousand from the budget.

According to the Center for Public Investigations, the relevant information is available in the Prozorro system.

The administration of Zavodskyi district of Mykolaiv City Council announced thefirst procurement in the format of open bidding with special conditions in late August. Since only one bidder applied for the tender, the local authorities did not have to choose the cheapest bidder. The agreement was to be signed with Mykolaivbudmekhanizatsiya, an additional liability company. The total amount, including price adjustments, was UAH 1 million 665 thousand.

For these funds, the contractor, according to the tender documents, was to dismantle the reinforced concrete massifs that had sagged due to soil leaching. It was also supposed to remove the defective concrete layer from the surface of concrete and reinforced concrete structures, remove construction waste, excavate the soil with an excavator, lay a layer of geotextile to prevent soil penetration, etc. In addition, it was necessary to install massifs to strengthen the bank, lay slabs and grout the joints of the retaining wall slabs. The work was to be completed by December 2, 2024.

However, on September 9, the website posted information about the tender's cancellation. The reason given was that there was no further need for the procurement.

The very next day, on September 10, the administration of Zavodskyi District of Mykolaiv City Council announced a new tender for coastal protection works in the Velyka Korenyha neighborhood with the same price. The auction was scheduled for September 18, but it did not take place due to a lack of bids.

Recently, the Mykolaiv Oblast Infrastructure Restoration and Development Service ordered the repair of the Varvarovsky Bridge over the Pivdennyi Buh River to the only bidder, European Road Construction Company LLC. The contract is worth UAH 57 million. The State Audit Service took an interest in the tender.

Ірина Глухова

Також Вам може сподобатись:

April 20, 2026

Former head of Mykolaiv Oblast Local Roads Agency released from punishment

In Mykolaiv, a National Guard officer avoids jail for selling volunteer cars

Mykolaiv region punishes invader for atrocities

Kherson's energy protection for a quarter of a billion was given to the firm of the ex-head of Zelenbud

More than half of coal procurement in Odesa region was shared by namesake companies

Mykolaiv region denies arrest of engineer for failure to repair heating networks

Doctors of Voznesensk medical institutions are under investigation

SBU uncovers informant network in Mykolaiv

April 19, 2026

Man sets fire to bank in Mykolaiv, smoking out FSB agent

Shelter in Belhorod-Dnistrovskyi gymnasium goes up by 5 million

Mykolaiv region has not been able to launch a donated boiler house for 2 years: donors plan to take the gift away

Legendary "cyborg" from Mykolaiv "Marshal" resigns as head of patrol police

The right to repair roads in Khadzhybeyskyi district of Odesa was given without an auction

Shahids hit Mykolaiv: two districts without electricity

Odesa Hospital Selects Contractor to Repair Roof for 28 Million