Million-dollar overpayments for water supply checked in Posad Pokrovsky

(PHOTO: restoration.gov.ua)

Law enforcement officers uncovered alleged misappropriation of budget funds during the reconstruction of infrastructure facilities in Posad Pokrovskyi. It concerns the reconstruction of the water supply system, where the cost of materials was overestimated, as well as incomplete completion of the work.

This was reported by the Center for Public Investigations.

The investigation focuses on a facility in the village of Posad-Pokrovske of the Chornobaiv community in Kherson district. After the destruction caused by the hostilities, a water supply restoration project was implemented here to provide local residents with basic utilities.

The investigation found that in November 2023, the Infrastructure Restoration and Development Service in Kherson region entered into an agreement with the contractor Agro Construction LLC. The contract provided for a set of works on the construction and restoration of pipelines and related engineering networks.

However, during the procurement analysis conducted by representatives of the public sector, serious inconsistencies were identified. In particular, they found overpricing of construction materials worth more than UAH 3.7 million. There are also suspicions that some of the work was not actually completed, although it was listed as completed in the documents.

Law enforcement officers are also checking information about the possible involvement of unregistered workers by the contractor to reduce costs. At the same time, funding from the budget was carried out in full - in accordance with the signed acts and payment documents.

As part of the pre-trial investigation, a construction and technical expertise has already been appointed. It should determine the actual scope of work performed and establish whether the funds spent correspond to the actual results.

The court allowed the investigators to access a wide range of documentation, including certificates of completion, a general construction log, and design materials with possible adjustments. These documents are expected to become important evidence and help identify those involved in the alleged abuses.

The investigation is ongoing under an article that provides for liability for misappropriation or embezzlement of property on a particularly large scale. Law enforcement officers are checking both the officials who coordinated the work and representatives of the contractor.

Also in April, the court extended the duties of Oleksandr Novokhatskyi, director of Budpostach-STSV. The company was a contractor in the project to reconstruct a shelter - a maternity unit on the territory of the Kherson City Perinatal Center. The contract was signed on August 6, 2024, and its total value exceeded UAH 101 million.

Анна Літман

You may also like:

Sept. 5, 2026

In Chornobaivka, Russian suicide bombers attacked a passenger train

The former head of the State Food and Consumer Service in Mykolaiv has become the face of the occupiers in the Kherson region

The daughter of Saldo, the so-called head of the Kherson region, has been accused of crimes against national security

Sept. 4, 2026

Community leader sentenced to 15 years for coordinating KAB airstrikes on the Kherson region

A collaborator from the Kherson region was brought to trial for torturing a woman with electric shocks

Kherson has allocated 400 million for the purchase of mobile shelters

In the Kherson region, a museum has filed a lawsuit over corruption in the restoration process

The director of the Balt Forest District was accused of embezzling public funds

Sept. 3, 2026

A Kuban-based giant is preparing to enter the agribusiness sector in the occupied Kherson region

The OVA has switched to 24-hour operations due to threats to business

Mykolaiv Oblast Found Itself at the Bottom of the NMT-2026 Ranking

Russian military personnel are disguising themselves as civilians on the Kinburn Peninsula

The commander of a Russian special forces unit has been charged with torturing an official in the Kherson region

Inverter + Battery: How to Build an Off-Grid Power System Advertisement

The family of a Kherson City Council member has accumulated $315,000 in cash