11 February 2026

Kherson region checks reconstruction of outpatient clinic for embezzlement

(An outpatient clinic. PHOTOS: IPC-North)

Law enforcement officers are investigating the possible misappropriation of budget funds during the reconstruction of an administrative building in Vysokopillya, which was to be converted into a family medicine outpatient clinic.

This was reported by Anti-Corruption Dimension with reference to a court ruling .

According to the court ruling, the customer of the work was the Department of Territorial Development of the Kherson Regional State Administration, and the contractor was Global Build Engineering. Despite the total cost of the project, the contractor has already received about UAH 34 million.

Investigators have now gained access to all financial and construction documentation to verify the actual scope of work performed and the validity of budget expenditures.

According to the Prozorro system (agreement No. 16-10/53), the total cost of works in the village of Vysokopillia, Beryslav district, is UAH 135.2 million. The investigation found that as of January 2026, the client had already transferred UAH 34 million to the contractor.

These payments have raised questions among law enforcement officers, who are currently checking whether the work actually performed corresponds to the scope and cost specified in official acts and estimates. The court recognized the case materials as essential for the investigation and granted investigators temporary access to the tender documents, additional agreements and payment orders with the possibility of seizing their copies.

In particular, the Kherson Regional Center for Educational Quality Assessment entered into a contract for the repair of its premises. The work will be performed by Kherson businessman <b>Serhiy Tisovskyi</b>.

The total amount of work under this contract is UAH 117,977. However, the contract attracts attention because of the contractor's controversial tender background.

According to the YouControl portal, Tisovskyi, who previously received small construction tenders, resumed his business in December 2023 and immediately received six repair contracts. His largest contract was for the repair of a storage facility in Novovorontsovka for almost UAH 2.9 million.

Катерина Глушко

You may also like:

Sept. 3, 2026

A deputy minister of the occupying authorities in Crimea has been barred from working for 10 years

A Kuban-based giant is preparing to enter the agribusiness sector in the occupied Kherson region

The OVA has switched to 24-hour operations due to threats to business

Mykolaiv Oblast Found Itself at the Bottom of the NMT-2026 Ranking

Russian military personnel are disguising themselves as civilians on the Kinburn Peninsula

The commander of a Russian special forces unit has been charged with torturing an official in the Kherson region

A court fined a resident of the Odesa region for organizing a network of illegal gas stations

Inverter + Battery: How to Build an Off-Grid Power System Advertisement

The family of a Kherson City Council member has accumulated $315,000 in cash

Sept. 2, 2026

The Odesa region will receive more than 260 million for teachers' salaries

A former director of a hospital in Kherson was found to have a "hidden" wife and forgotten assets

In Ukraine, air raid alerts will be classified as yellow or red levels

In the Kherson region, bail was set for three officials in the "dead souls" case

Following the death of a worker at the grain terminal in Reni, documents were seized

Kherson Approves Budget for a Three-Year Plan to Rebuild and Protect the Community