April 6, 2026, 10:01 a.m.

Embezzlement in elevator procurement exposed in Mykolaiv

(PHOTO: brovary.net.ua)

In Mykolaiv, a trial is underway against an official of the city council's housing and communal services department, who is accused of embezzling budget funds. The case concerns the possible overstatement of the cost of elevator equipment during the overhaul of apartment buildings.

This is evidenced by the ruling of the Zavodskyi District Court of Mykolaiv.

According to the investigation, in 2016, passenger elevators manufactured by OJSC Mogilev Elevator Plant (Belarus) were purchased. Earlier examinations established that their cost was about UAH 207-218 thousand excluding VAT, but the total amount of possible overpricing could have reached almost UAH 900 thousand.

At the same time, the newer 2025 expertise showed a much higher market range - from 330 to 440 thousand hryvnias per elevator. Due to these discrepancies between the experts' conclusions, the prosecutor in court insisted on conducting a second comprehensive commodity and economic examination.

The defense team and the defendant did not object, but insisted on involving another expert institution. They also stated that there was no overpricing, and the cost of the equipment was in line with market conditions at the time.

The judge partially granted the prosecutor's motion and ordered a new examination. The experts of the Volyn Branch of the Lviv Scientific Research Institute of Forensic Expertise were commissioned to conduct it.

The experts were asked a number of key questions, including

The results of the new examination may be decisive for establishing the fact of violations and the further fate of the case.

Also in April, a scheme was uncovered in Pivdenoukrainsk during the repair of heating networks, which resulted in the loss of more than UAH 6 million to the city budget. According to the investigation, the fraud involved the director of the contractor and the chief engineer of the project, who agreed on questionable changes and overestimated the cost of the work.

Анна Бальчінос

Також Вам може сподобатись:

April 6, 2026

Glorifier of Russia in Odesa is on probation for three years

Russian fan from Kherson paid with apartment and car for propaganda

April 5, 2026

Action in memory of fallen soldiers held in Mykolaiv region

Language testing center opened in Mykolaiv

Transport that operated in Odesa during the blackout returned to Mykolaiv

Odesa resident convicted in Chernihiv for arson ordered by Russia

Shelling of Kherson and Mykolaiv regions: dead, wounded, including a child

April 4, 2026

In three months, 200 thousand tons of shell rock were illegally dug in Odesa region

Mykolaiv region farmers get a chance for revival after Kakhovka HPP explosion

Prosecutor dismissed for bribery in Odesa region

Mykolaiv received 26 new buses on credit for EUR 4.5 million

Occupants arrest 26 Crimean residents for treason

Reconstruction of boiler houses in Voznesensk was awarded to a contractor with a history of overpayments

Only Odesa City Council did not answer how much it spent on the Defense Forces

Beaten with truncheons and kicked: occupation security forces exposed for torture in Kherson