25 July 2025

Boiler houses worth a billion were ordered in Mykolaiv without open bidding

(PHOTOS: Suspilne)

Mykolaiv Regional Electricity Company signed agreements worth more than one billion hryvnias for new boiler houses to replace the destroyed CHP plant. The contracts for the supply of equipment were signed without open bidding with five companies.

This is evidenced by data from the Prozorro procurement system.

The Department of Urban Planning, Architecture, Capital Construction and Development Project Support of the Mykolaiv Regional Military Administration has signed five agreements for the supply of block-modular boiler houses totaling more than UAH 1.8 billion. All contracts were executed without open bidding, which is allowed in wartime in accordance with government regulations.

In particular, the following agreements were concluded

In total, it is planned to supply 18 block-modular boiler houses of various capacities to be delivered by November 28, 2025. The equipment must be new, not older than 2025, and all materials must be corrosion-resistant.

The justification states that the decision to make the procurement without the Prozorro electronic system was made due to an urgent need, confirmed by the protocols of the working group and the order of the head of the Military Department under martial law. The goal is to promptly provide alternative heat in the region to replace the destroyed CHPP.

On the night of February 16, Russians massively shelled Mykolaiv, causing a fire to break out at a critical facility, the Mykolaiv CHP. The attack left part of the city without heat and electricity. Mayor Oleksandr Sienkevych said that the CHP plant was attacked deliberately to leave the city without heating during the cold weather.

More than 15,000 square meters of land were contaminated by the munitions and 120 square meters of waste was generated. The damage was estimated at UAH 536 million.

In May, the CHPP ordered equipment repairs for UAH 23 million without a tender. Converter-Complex was to restore the destroyed turbine generators and prepare design and estimate documentation.

Анна Бальчінос

You may also like:

June 19, 2026

The Odesa Regional State Administration selected a bus supplier for 109 million without an auction

In Mykolaiv, part of a rehabilitation center was leased without a bidding process

How a Gold Ring Is Made: A Look Inside a Handcrafted Workshop Advertisement

An official from the Mykolaiv region stole money and fled abroad

June 18, 2026

Mykolaiv Maternity Hospital No. 3 will receive 5.5 million

A defender from Mariupol has taken charge of a new veterans' center in the Mykolaiv region

Hospital management is being reformed in the Mykolaiv region

A company accused of fraud won a 110-million contract to repair roads leading to Ovidiopol

In the Mykolaiv region, a Ukrainian language teacher has been nominated for a Verkhovna Rada award

The Mykolaiv Maternity Hospital Will Receive Over 5 Million

June 17, 2026

The Mykolaiv Maternity Hospital Has Accumulated Millions in Debt

A support center for veterans and their families will be established in the Mykolaiv region

A company suspected of corruption is bidding to renovate a high school in the Odesa region

When everything is in its place, or when accessories are chosen just right—and their magic Advertisement

In Mykolaiv Oblast, teachers are being forced to clean the streets: the ombudsman is demanding an explanation