25 July 2025

Boiler houses worth a billion were ordered in Mykolaiv without open bidding

(PHOTOS: Suspilne)

Mykolaiv Regional Electricity Company signed agreements worth more than one billion hryvnias for new boiler houses to replace the destroyed CHP plant. The contracts for the supply of equipment were signed without open bidding with five companies.

This is evidenced by data from the Prozorro procurement system.

The Department of Urban Planning, Architecture, Capital Construction and Development Project Support of the Mykolaiv Regional Military Administration has signed five agreements for the supply of block-modular boiler houses totaling more than UAH 1.8 billion. All contracts were executed without open bidding, which is allowed in wartime in accordance with government regulations.

In particular, the following agreements were concluded

In total, it is planned to supply 18 block-modular boiler houses of various capacities to be delivered by November 28, 2025. The equipment must be new, not older than 2025, and all materials must be corrosion-resistant.

The justification states that the decision to make the procurement without the Prozorro electronic system was made due to an urgent need, confirmed by the protocols of the working group and the order of the head of the Military Department under martial law. The goal is to promptly provide alternative heat in the region to replace the destroyed CHPP.

On the night of February 16, Russians massively shelled Mykolaiv, causing a fire to break out at a critical facility, the Mykolaiv CHP. The attack left part of the city without heat and electricity. Mayor Oleksandr Sienkevych said that the CHP plant was attacked deliberately to leave the city without heating during the cold weather.

More than 15,000 square meters of land were contaminated by the munitions and 120 square meters of waste was generated. The damage was estimated at UAH 536 million.

In May, the CHPP ordered equipment repairs for UAH 23 million without a tender. Converter-Complex was to restore the destroyed turbine generators and prepare design and estimate documentation.

Анна Бальчінос

You may also like:

July 9, 2026

In Mykolaiv, there is talk of a shortage of funds for salaries in the cultural sector

The Odesa region plans to spend more than 100 million on renovating a high school building

Mykolaiv's Housing and Utilities Department Will Spend 16 Million on Its Own Shelter

An advisor to the mayor of Mykolaiv accused a colleague of sabotaging the moment of silence

Residents of Mykolaiv are demanding that an unfinished gas station be demolished

How the War Changed Men's Approach to Job Hunting in 2026 Advertisement

A programmer from the Mykolaiv region will pay an 84,000 fine for a payment deferral scheme

July 8, 2026

In Mykolaiv Oblast, authorities are seeking to reclaim illegally leased properties worth nearly 30 million

Mykolaivvodokanal and the Port of "Pivdennyi" Have Been Designated as Monopolies

Mykolaiv Found 60 Million to Ensure Kindergartens Don't Run Out of Food

The TOP 20 Effect: How a Single Honest Review Can Change the Fate of a Local Business Advertisement

The number of building permits in Mykolaiv rose by 60%

In Pivdennoukrainsk, city council members held a session after a long hiatus

The Time-Squeeze Trap: Why We Overpay Because of Haste, Not Because of Price Tags Advertisement

An athlete from the Mykolaiv region became the European champion in Greco-Roman wrestling