21 November 2026, 16:01
None of the 19 renovated homes in Posad-Pokrovskyi have been handed over to their owners
Ця стаття також доступна українською
Work on rebuilding the village. Photo: Oleksiy Kuleba/Facebook
In Posad-Pokrovskyi, in the Kherson region, 12 private homes have been fully constructed and another 7 have undergone major renovations; however, none of them have yet been put into service or handed over to their owners.
This was reported by Vgoru.
As part of the village’s comprehensive reconstruction, there are plans to rebuild 362 private residential homes. Of these, 263 are to be rebuilt from scratch, and 99 are to be restored through major renovations.
This is a state-funded pilot project launched in 2023. It involves the reconstruction of housing, social infrastructure, and utility networks.
According to the Infrastructure Restoration and Development Service in the Kherson region, as of November 18, 2026:
- 84 newly constructed buildings and 49 buildings undergoing major repairs are in the final stages;
- construction is continuing on another 142 buildings, and major repairs are underway at 21 sites;
- work has not yet begun on 47 sites: 25 are slated for new construction, and 22 for major repairs.
The Service cited organizational, technical, legal, and personnel-related reasons. At some sites, residents are hindering construction, and some owners have changed their minds about participating in the restoration. Some properties have been seized, and at certain buildings, the restoration method must be revised due to the technical condition of the structures.
Read also: Reconstruction of Posad-Pokrovsky: A Village Destroyed by the Russians Is Being Restored to Life
Contractors are also facing a shortage of skilled workers. The Service attributes this to mobilization measures, difficulties in replacing staff, and workers relocating to other communities.
What Is Known About the Criminal Cases Related to the Reconstruction
The reconstruction in Posad-Pokrovskyi has already become the subject of criminal investigations.
Recently, the prosecutor’s office demanded that the contractor return more than 547,000 hryvnias to the budget.
The director of the construction company and the technical supervision engineer will also face trial; according to the prosecutor’s office, they caused nearly 2 million hryvnias in losses to the state.
In addition, a 49-year-old representative of the Reconstruction Service will face trial for official negligence for failing to oversee the construction of 13 buildings and failing to verify the certificates of completion.