The Service for Infrastructure Restoration and Development in Odesa Oblast has selected the private company DISK-Pivden, which had previously been involved in the restoration of the nine-story building in Serhiivka damaged by the Russians, as the contractor to carry out additional work on the building.

The relevant information is available in the Prozorro electronic procurement system, according to the Center for Public Investigations.

The procurement was conducted in the format of an open tender with special conditions, and DISK-Pivden was the only participant. The company expects to receive UAH 45 million 949.2 thousand for additional repairs to the building. The completion date for these works is set for December 31, 2025.

The nine-story building in Serhiivka, Odesa Oblast, was destroyed on July 1, 2022. Then the Russians fired three X-22 missiles at the village - one of them hit the basement of the building. The explosion completely destroyed the first entrance, while the other two were severely damaged. 105 out of 106 apartments in the nine-story building were destroyed. Restoration of the building began on December 1, 2023.

In December 2023, the Infrastructure Restoration and Development Service in Odesa Oblast found a contractor to carry out major repairs to a multi-storey building in Serhiivka, Odesa Oblast, that was damaged by a Russian missile attack in June 2022.

The tender was announced on November 7. The expected value of the procurement was UAH 75 million 55 thousand. The tender was won by DISK-Pivden, which offered UAH 73 million 550 thousand for its services.

According to the results of the tender, the Infrastructure Restoration and Development Service in Odesa Oblast entered into an agreement with DISK-Pivden. The company was to carry out major repairs of a multi-storey building in Serhiivka by December 31, 2024.

It should be noted that the State Audit Service of Ukraine published its own rating of the ten most expensive procurements for the restoration of civilian facilities affected by the aggression of the Russian Federation announced in late November, which was headed by two tenders from Odesa region.

Кирило Бойко

Share