22 November 2026, 11:28

The contract for a daycare center in Odesa was not terminated due to a mistake by the prosecutor

Ця стаття також доступна українською

PHOTO: FB/Oleksandr Ivanytskyi

PHOTO: FB/Oleksandr Ivanytskyi

The Court of Appeals dismissed the lawsuit seeking to terminate the contract for the construction of a kindergarten in Odesa because the prosecutor filed it on behalf of an ineligible plaintiff. The agreement between the Capital Construction Department and the company “Monolit” has remained in limbo, without funding or work, since the end of 2025.

This is stated in a ruling by the Southwestern Commercial Court of Appeals.

The parties signed the contract for the construction of a kindergarten in Odesa back in November 2023. According to the documents, the cost of the work amounted to over 143.8 million hryvnias.

The contract’s term was extended several times through supplementary agreements—most recently until December 31, 2025. After that date, no new agreements were signed, no funds were allocated from the budget, and construction work came to a halt. No report on the contract’s implementation was published in the Prozorro system either.

See also:In Odesa Oblast, inflated prices were discovered in the construction of a shelter for a kindergarten

The Capital Construction Department confirmed the lack of funding and work. However, they maintained that the contract remains formally in effect until the parties fulfill all their obligations.

The Khadzhibey District Prosecutor’s Office in Odesa intervened in the situation. The prosecutor determined that such an unresolved contract posed risks to the city budget. He filed a lawsuit in the interest of the state, represented by the Odesa City Council, and demanded that the contract be declared terminated.

In September, the Odesa Regional Commercial Court dismissed the claim, after which the prosecutor’s office filed an appeal. A panel of judges overturned the previous decision but also declined to consider the merits of the case.

Read also:In Odesa Region, a contractor was re-selected for the construction of a shelter at a kindergarten

The court explained that the prosecutor had committed a procedural error. The contract with “Monolit” was signed by the Capital Construction Department as a separate legal entity, not by the Odesa City Council itself. The law does not grant the city council the authority to demand the termination or cancellation of agreements entered into by third parties. 

As a result, the prosecutor’s lawsuit was dismissed, and the contract for the construction of the kindergarten retained its previous status.

Юлія Калабайда