Restoration of the Jewish Hospital in Odesa for an EU loan: journalists reveal inflated prices in the estimate

(Photo: google.maps)

In Odesa, the city council has chosen a contractor to restore the surgical pavilion of Hospital No. 1, known as the Jewish Hospital. The tender was attended by a single bidder, so the Capital Construction Department did not have to choose between the cheaper bidders.

As reported in the Prozzoro system, on September 13, the agreement was signed with Exterior Design LLC. The value of the contract for price adjustment is UAH 167 million 938 thousand.

The project involves large-scale works: repair of facades, interior decoration, installation of water supply, ventilation, heating, alarm systems, etc. The total cost of the work is financed by a loan from the European Investment Bank, and VAT is covered by the local budget.

Investigative journalists from the Nashi Hroshi publication found serious overestimates of prices for construction materials and equipment in the estimate. For example, rebar was priced at UAH 66,461 per ton, although its value on the market is two times lower. In particular, Metinvest-SMC LLC's online metal-roll store sells such rebar at UAH 29,110/t, while Odesa-based Zenit metalware offers it at UAH 33,400/t.

Prices for expanded polystyrene, curb stones and gas blocks are also overpriced, by 15-73% more than market prices.

BR 100.20.8 curb stones were priced at 299 UAH/unit. Recently, the Zaporizhzhia-based utility Eluash ordered them at 180 UAH/each, and the Kyiv-based utility Road Maintenance Department for the Repair and Maintenance of Roads and Facilities in Darnytsia District at 201 UAH/each, which is 33-40% cheaper, the investigators write.

In addition, a gas block measuring 150x200x600 was priced at UAH 4,709 per cubic meter. The online store "TBC Alex-Group" offers such aerated concrete at a wholesale price of UAH 3,210 per cubic meter, and "Epicenter" in Odesa offers such blocks at UAH 4,000 per cubic meter, which is 15-32% cheaper than in the estimate.

The indicated average salary of workers (UAH 13,708) was lower than the real average salary in construction in Odesa (UAH 23,000), which also raises questions about the transparency of the estimate.

Earlier, the reconstruction of Odesa Maternity Hospital No. 5, for which UAH 175 million was allocated, attracted the attention of journalists due to possible overpricing of construction materials and equipment. The project is being financed by a loan from the European Investment Bank, with VAT covered by the local budget.

Ірина Глухова

Також Вам може сподобатись:

April 24, 2026

New interim head appointed to Odesa Zoo

Director of municipal enterprise in Odesa region sent to pre-trial detention center

Odesa residents met with the most famous science fiction writers of the country

Accent figured out what's next for the Odesa Zoo

IT sector of Odesa region today: what helps to work in the face of staff outflow and blackouts

30 tons of soybean cargo disappeared from a port in Odesa region

Odesa approves the design of tombstones at the memorial to the fallen

193 soldiers returned to Ukraine from Russian captivity

Ready-made housing vs. investments in the pit: how the war has changed the buyer's logic Реклама

Court puts an end to the case of Chornomorsk port

Judge from Odesa region suspended from work for not returning from Norway

The number of companies without claims from the tax authorities has increased in Odesa region

Spouses killed in night attack in Odesa

April 23, 2026

Romania takes control of Giurgiulesti port near Odesa region

Odesa approves restoration of architectural monuments in three lyceums