04 January 2025

Repair of Odesa boiler house pipe will cost more than planned

(Photo: Odesa City Council)

The reconstruction of the chimney of Odesa's Pivnichna-2 boiler house, which collapsed during bad weather, has risen in price by almost UAH 2.5 million.

This was reported by the Center for Public Investigations.

On January 2, the Odesa City Heat Supply Utility signed a contract with Inventum Ukraine on the Prozorro platform without a tender procedure.

Adjustments usually relate to additional costs that arise due to an increase in the scope of work or rising prices for materials. The contractor has to complete the work by February 28.

In August last year, the same company was awarded a contract for "Additional Works" for the same facility, with a total value of UAH 2.4 million.

In the summer, Odesa began reconstructing the pipe of the Severnaya-2 boiler house, which collapsed during a strong wind last year. According to Mayor Gennadiy Trukhanov, UNICEF allocated UAH 60 million for the repairs. The construction was planned to be completed by November 1, 2024. This was described in detail by the CPR in its article.

Inventum Ukraine was registered in 2009 in Sumy. The founders of the company are three people: Hlib Minenko, Zhanna Talats and Oleksandr Hnapovsky. This is not the first time the company has entered into budgetary agreements, having already signed contracts totaling almost UAH 385 million. In 2018, Inventum Ukraine LLC was involved in a criminal investigation into the possible misappropriation of funds during the restoration of the boiler unit at Sumy CHP for UAH 17.5 million. In addition, in 2016, the company's accountant was tried for tax evasion of more than UAH 620 thousand. She was released from criminal liability because she had paid everything at the time of the trial.

On the night of November 27, 2023, a chimney more than 100 meters high, which belonged to the Pivdenna-2 boiler house, collapsed in Odesa due to hurricane winds. The incident occurred during bad weather.

An expert examination conducted in January 2024 revealed that the chimney collapse was caused by the poor quality of construction work during its construction. The study showed heterogeneity in the concrete, with samples having different strengths depending on the site. The conclusion of the experts was unequivocal: it was impossible to restore this pipe, and a new structure had to be built.

Ірина Глухова

You may also like:

June 11, 2026

Izmail will spend an additional 16 million on renovating a building to serve as a dormitory for displaced persons

Changes to parking regulations, electronic tickets, and small retail kiosks were discussed in Odessa

In the Odessa region, executives of a municipal enterprise will stand trial for a scheme involving the extortion of septic tank cleaners

St. Nicholas Monastery in Izmail: The History of a Shrine Older Than the Fortress

In Odessa, a company director admitted to accepting bribes and helped expose an official at a health resort to the SBU

From flight jacket to women’s wardrobe: a brief history of the bomber jacket and its Ukrainian reinterpretation Advertisement

In Odessa, 4 billion has been allocated for the "Safe City" program

The SBU has exposed a Russian intelligence officer for recruiting teenagers in Odesa

Laptops—up to 50,000, phones—up to 10: Odessa revises rules for the use of budget funds

How to verify that the backup system is configured correctly Advertisement

The Odessa City Executive Committee has outlined measures to support national defense, veterans, and residents of high-rise buildings

5,000 cannabis plants were found in a national park in the Odessa region

The State Bureau of Investigation searched the car of Borisov, the former head of the Odessa Regional Anti-Corruption Center

In Odessa, a former police officer pleaded guilty to making pro-Russian statements

June 10, 2026

Trading of military posts in the rear exposed in Odessa