The reconstruction of the chimney of Odesa's Pivnichna-2 boiler house, which collapsed during bad weather, has risen in price by almost UAH 2.5 million.

This was reported by the Center for Public Investigations.

On January 2, the Odesa City Heat Supply Utility signed a contract with Inventum Ukraine on the Prozorro platform without a tender procedure.

Adjustments usually relate to additional costs that arise due to an increase in the scope of work or rising prices for materials. The contractor has to complete the work by February 28.

In August last year, the same company was awarded a contract for "Additional Works" for the same facility, with a total value of UAH 2.4 million.

In the summer, Odesa began reconstructing the pipe of the Severnaya-2 boiler house, which collapsed during a strong wind last year. According to Mayor Gennadiy Trukhanov, UNICEF allocated UAH 60 million for the repairs. The construction was planned to be completed by November 1, 2024. This was described in detail by the CPR in its article.

Inventum Ukraine was registered in 2009 in Sumy. The founders of the company are three people: Hlib Minenko, Zhanna Talats and Oleksandr Hnapovsky. This is not the first time the company has entered into budgetary agreements, having already signed contracts totaling almost UAH 385 million. In 2018, Inventum Ukraine LLC was involved in a criminal investigation into the possible misappropriation of funds during the restoration of the boiler unit at Sumy CHP for UAH 17.5 million. In addition, in 2016, the company's accountant was tried for tax evasion of more than UAH 620 thousand. She was released from criminal liability because she had paid everything at the time of the trial.

On the night of November 27, 2023, a chimney more than 100 meters high, which belonged to the Pivdenna-2 boiler house, collapsed in Odesa due to hurricane winds. The incident occurred during bad weather.

An expert examination conducted in January 2024 revealed that the chimney collapse was caused by the poor quality of construction work during its construction. The study showed heterogeneity in the concrete, with samples having different strengths depending on the site. The conclusion of the experts was unequivocal: it was impossible to restore this pipe, and a new structure had to be built.

Ірина Глухова

You may also like:

Sept. 7, 2026

The newly appointed head of the Peresyp District in Odesa had a business in the housing and utilities sector

The High Anti-Corruption Court arrested the former deputy dean of the Odesa Law Academy in connection with the "Carthage" case

The Odesa region ranked fourth in Ukraine in terms of the number of companies with tax debts

A former associate dean of the Odesa Law Academy has resurfaced in the “Carthage” case

Sept. 6, 2026

Ukrainian exporters were urged to take a survey on problems at Romanian ports

Ukrainian Instead of Russian: How a New Generation of Children Is Being Raised in Odesa

Linguist Orisa Demska assessed the chances of Odessa regaining its linguistic multiculturalism

Kropiva, the former deputy head of the Odesa Regional State Administration, was remanded in custody with bail set

Saudi grain giant has cut back on barley imports from the Black Sea region

A lawmaker from the Odesa region failed to disclose a foreign passport and assets worth 6 million in his financial disclosure statement

An official from the Trade and Commerce Commission was caught abusing his influence in Odesa

Companies owned by an Odessa lawmaker were awarded a 64-million contract to repair the highway without any competition

Sept. 5, 2026

The Cabinet of Ministers has changed the rules for agricultural exports due to Russian aggression in the Black Sea region

The winners and recipients of the Golden Duke were announced at the 17th Odessa Film Festival

Construction of an agricultural park costing 884 million hryvnias has been approved in the Odesa region