07 March 2025

Mykolaiv Court Invalidates ₴1.4M Loader Contract for Quality Issues

(PHOTOS: Channel 24)

A Mykolaiv court invalidated a contract for the purchase of a telescopic loader that did not meet the requirements and ordered a refund. A utility company in the Bashtanka region spent almost one and a half million for low-quality vehicles.

This was reported by the press service of the Mykolaiv Regional Prosecutor's Office.

The Economic Court of Mykolaiv Oblast upheld the claim of the Bashtanka District Prosecutor's Office, which acted in the interests of the state and local authorities, and invalidated the contract between the utility company and a private entrepreneur for the purchase of a telescopic loader.

It turned out that the utility company purchased the loader for UAH 1.4 million through a public procurement, but it did not meet the technical requirements: it did not meet the year of manufacture, service life, and standards for localization of production in Ukraine.

According to the court's decision, the entrepreneur must return the money received for the forklift, and the utility company is obliged to return the goods. This decision will help the government better control budget spending.

In Mykolaiv, the head of a private company and a technical supervision engineer are accused of embezzling almost UAH 39.5 million during the construction of a pontoon bridge. The Southwestern Commercial Court of Appeal upheld the prosecutor's claim and ordered the return of state property worth UAH 2 million.

The prosecutor's office also challenged supply agreements to social institutions due to collusion of entrepreneurs in Mykolaiv region and demanded a refund. They are accused of manipulating the bidding process and distorting the procurement results.

Recently, the court canceled an agreement with a contractor who did not start construction of a stadium despite the allocation of more than UAH 17 million. The Department did not take appropriate measures to monitor the fulfillment of the contract, which indicates ineffective management of budget funds during martial law.

Анна Літман

You may also like:

Aug. 28, 2026

A food supply scheme for closed schools was uncovered in the Mykolaiv region

Three prosecutors from Crimea were sentenced for treason

A court in Odesa found a man guilty of operating a shell company

A resident of the Kherson region was notified of charges of indoctrinating children during the occupation

Agricultural enterprises in the Mykolaiv region increased production by 27 percent

In Pervomaisk, a sole proprietor bought up the water utility’s old debts and is suing residents to collect them

Housing construction in the Mykolaiv region increased by 80 percent

In Odesa, the tax authorities secured a rehearing of the case involving the supply of corn worth 27 million

Aug. 27, 2026

A court in Odesa ordered the seizure of the former director’s shares in five of the country’s water utilities

In the Mykolaiv region, nearly 94 percent of children will attend school in person or through a hybrid model

The High Anti-Corruption Court scheduled a hearing in the case involving false information in an Odesa lawmaker's financial disclosure form

In Mykolaiv, a lawsuit was filed against the owner of a historic mansion, demanding that a preservation agreement be signed

Aug. 26, 2026

As part of a special operation in Odesa, five warehouses containing drugs were uncovered

In Odessa, a man challenged his mobilization due to a questionable medical examination

Aug. 25, 2026

A new head of the municipal enterprise has been appointed in Odesa