A boiler house reconstruction project was presented in Mykolaiv, which involves the installation of a gas cogeneration unit to improve the city's heat supply. More than UAH 4 million of the required UAH 18 million was allocated from the local budget for the project.

This was reported by the Center for Public Investigations with reference to the DREAM ecosystem.

It is planned to reconstruct the boiler house on Sportyvna Street. The project involves the technical re-equipment of the facility with the installation of a gas cogeneration unit. The project will help reduce CO₂ emissions, cut energy costs and ensure a stable supply of heat and electricity for the city.

Screenshot: DREAM

The main objectives of the project:

According to the description, the project will contribute to the economic development of Mykolaiv through the introduction of modern energy technologies. The use of cogeneration technology will reduce the load on the city's power system and provide electricity to critical infrastructure facilities.

The total budget for the reconstruction is UAH 18 million. Part of the funding - UAH 4.1 million - has already been confirmed from the local budget. However, additional funds, including possible investments and grants, need to be raised to complete the work.

Screenshot: DREAM

The modernization of the boiler house in Mykolaiv is a strategically important project for the city, which will optimize the heat supply system, reduce financial costs, and improve the environmental situation. Thanks to the use of cogeneration technology, residents will receive better and more stable heat supply, and the city will have an energy-efficient and modern infrastructure.

Mykolaiv also presented a project to improve energy efficiency in the Namiv neighborhood, which involves the installation of individual heating points in high-rise buildings. The initiative will last for two years with a total budget of UAH 70.9 million.

Meanwhile, the village of Novopetrivka, Mykolaiv region, will start reconstructing the water supply system destroyed during the occupation. It is planned to drill an artesian well, install pumping equipment and two new water towers, and part of the funding of UAH 3 million has already been provided by Germany.

Анна Бальчінос

Також Вам може сподобатись:

Feb. 19, 2026

Psychotropic drugs worth one million hryvnias seized in Mykolaiv during special operation Rubicon

Germany invests one million euros in energy security of Kherson region

Feb. 18, 2026

Mykolaiv Alumina Plant to be put up for sale as a priority

Feb. 17, 2026

Pervomaisk to appeal to the Cabinet of Ministers over 50 million debt to teachers

High Council of Justice approves dismissal of judge from Mykolaiv

Denmark has invested $430 thousand in technical education for Mykolaiv residents

Mykolaiv region: woman attempts to blow up car of AFU commander

Feb. 16, 2026

Prosecutor's Office calls death in road accident with Voznesensk mayor a fake

Snowmelt floods 17 settlements in Mykolaiv region

A large foster family from Mykolaiv received a new home

Mykolaiv region reveals violations in the vast majority of procurements of the month

Feb. 15, 2026

Athlete from Mykolaiv unfurled the city's flag at the highest point in Africa

Mykolaiv City Council Lacked Funds to Pay Salaries to Education Workers

Government allocates 10 million to Dobroslav community for shelter

Feb. 14, 2026

Mykolaiv rejects complaint about misappropriation of funds for water intake repair