March 21, 2025, 10:27 a.m.

Mykolaiv Allocates ₴4.1M for Boiler House Reconstruction with Gas Cogeneration Unit

(PHOTO: Dream)

A boiler house reconstruction project was presented in Mykolaiv, which involves the installation of a gas cogeneration unit to improve the city's heat supply. More than UAH 4 million of the required UAH 18 million was allocated from the local budget for the project.

This was reported by the Center for Public Investigations with reference to the DREAM ecosystem.

It is planned to reconstruct the boiler house on Sportyvna Street. The project involves the technical re-equipment of the facility with the installation of a gas cogeneration unit. The project will help reduce CO₂ emissions, cut energy costs and ensure a stable supply of heat and electricity for the city.

Screenshot: DREAM

The main objectives of the project:

According to the description, the project will contribute to the economic development of Mykolaiv through the introduction of modern energy technologies. The use of cogeneration technology will reduce the load on the city's power system and provide electricity to critical infrastructure facilities.

The total budget for the reconstruction is UAH 18 million. Part of the funding - UAH 4.1 million - has already been confirmed from the local budget. However, additional funds, including possible investments and grants, need to be raised to complete the work.

Screenshot: DREAM

The modernization of the boiler house in Mykolaiv is a strategically important project for the city, which will optimize the heat supply system, reduce financial costs, and improve the environmental situation. Thanks to the use of cogeneration technology, residents will receive better and more stable heat supply, and the city will have an energy-efficient and modern infrastructure.

Mykolaiv also presented a project to improve energy efficiency in the Namiv neighborhood, which involves the installation of individual heating points in high-rise buildings. The initiative will last for two years with a total budget of UAH 70.9 million.

Meanwhile, the village of Novopetrivka, Mykolaiv region, will start reconstructing the water supply system destroyed during the occupation. It is planned to drill an artesian well, install pumping equipment and two new water towers, and part of the funding of UAH 3 million has already been provided by Germany.

Анна Бальчінос

You might also like:

Jan. 9, 2026

Mykolaiv deputies plan to appeal to the Verkhovna Rada on taxes

Agent of aggressor state gets 9 years in prison in Mykolaiv

Pervomaisk plans to attract 168 million in state subsidies for education

Mykolaiv region reveals overpayments in construction of shelter for children for 85 million

TCC official exposed in Mykolaiv for violence against conscripts

Jan. 8, 2026

Million-dollar corruption scheme organized at Mykolaiv power grid repair

Ukrainian business has rethought solar energy: from saving to survival Advertising

Mykolaiv region resident accuses TCC of kidnapping

Jan. 7, 2026

Mykolaiv lacks one billion in funding: city council appeals to the Government

Mykolaiv region: Police detain man for possession of weapons arsenal

Jan. 6, 2026

A couple sold their newborn child in Mykolaiv

Prosecutor's Office announces suspicion to occupier for torturing residents of Mykolaiv region

Jan. 5, 2026

Kherson approves community development program for 2026-2028

Mykolaiv region raises gas delivery tariff for enterprises

Mykolaiv region wants to close a kindergarten due to lack of shelter