Sept. 24, 2025, 4:02 p.m.

It took 300 million to prepare Odesa for the heating season

(Repair of heating networks in Odesa. PHOTO: Municipal enterprise "Heat supply of the city of Odesa" / Facebook)

This year, Odesa City Heat Supply spent hundreds of millions on procurement. These include the construction of a cogeneration unit, repair of boilers and pipes, and preparation for the heating season.

Intent analyzed the largest deals through the Zakupivli.pro platform .

In 2025, the utility company Odesa Heat Supply spent city budget funds on large-scale purchases and repairs. The lion's share of expenditures was for energy services, equipment, and preparations for the heating season.

The most expensive procurement at the beginning of the year was electricity distribution and reactive energy flow services, with a plan to spend over UAH 114 million. At the same time, the company invested heavily in the installation of electric heating systems and household equipment: over 4 million at 80-B Heroiv Defyny Odysey Street and 3.2 million at 45a Akademika Korolyova Street. The installation of the electrical part alone at the same address cost over 38 million.

Construction and repair works were a separate cost item. The overhaul of the pumping station building at 76 Mechnikova Street was estimated at UAH 2.4 million, the reconstruction of the flue gas removal system at Pivdenna-2 boiler house at UAH 2.5 million, and the repair of the recirculation system of boilers at Chubaivka boiler house at UAH 1.4 million.

More than UAH 20 million was allocated for the current repair of the PTVM-100 boiler at Severnaya-1 boiler house, and another UAH 12 million was allocated for the reconstruction of Severnaya-2 boiler house. In July, almost UAH 44 million was spent on preparing the facilities for the heating season, including the construction of a power generation system based on cogeneration units.

We also spent money on equipment: UAH 22 million was spent on the purchase of pipes, flanges and bends, UAH 12 million on hydraulic testing of networks, and more than UAH 5 million on maintenance of gas and heat metering units.

In the second half of the year, the company continued to spend budget funds on modernization and winterization. In particular, UAH 8.7 million was allocated to repair the facade of the administrative building using energy-saving technologies.

Almost UAH 7 million was spent on the purchase of cables, and another UAH 11.6 million was spent on the temporary connection of the cogeneration unit to the power grid. Additionally, more than 4 million was allocated for the reconstruction of the power grids for its full connection. In September, the utility company announced several tenders for the overhaul of pumping equipment at Chubayivka, Pivnichna-2 and Pivdenna-2 boiler houses, which together cost almost UAH 20 million.

Thus, since the beginning of 2025, Odesa Heat Supply Utility has spent UAH 296.3 million on the most expensive procurements alone.

At the same time, Khersonteploenergo spent more than UAH 152 million on the most expensive procurement. Most of the money was spent on electricity and its distribution, repair of water supply systems and purchase of diesel fuel.

Анна Бальчінос

Також Вам може сподобатись:

April 26, 2026

Former editor-in-chief of Odesa Film Studio tells about underground exhibitions of the 70s

Odesa MPs declared almost 4 thousand square meters of real estate

The buyer of the Nika Spirit tanker in Odesa region failed to sell it at a discount

Odesa resident failed to cancel evidence of his high treason

An earthquake struck near Odesa region

Odesa continued to develop the exhibition on Deribasovskaya Street

Odesa deputy accuses ex-zoo director of inciting hatred against her

A ship flying the flag of Palau was damaged in an attack in the port of Chernomorsk

Izmail decided to turn the shipping company building into housing for IDPs

Russian drone hits oil tanks in Odesa region

April 25, 2026

Former tax officer in Odesa convicted for old bribe

Amazing South: Amazon in Odesa region

Former Deputy Prosecutor General from Odesa failed to prove that his income was reasonable

Five richest MPs from Odesa declared 27 million

Odesa MPs declare fur coats, diamonds and real estate abroad