In Odesa, a contractor was charged in connection with the renovation of a kindergarten

(Kindergarten No. 45 in Odesa. PHOTO: osvita-omr.gov.ua)

While setting up a shelter at one of Odessa’s kindergartens, law enforcement officials discovered a possible overpricing of the work. According to investigators, the documents contained information that did not correspond to the actual quantities and specifications of the equipment.

The Center for Public Investigations uncovered the details of the case.

As stated in the court ruling, on June 27, 2025, Kindergarten No. 45, the Municipal Enterprise “Center for Financing and Economic Activities of Educational Institutions in the Peresypsky District of Odessa,” and a contractor entered into a contract for the major renovation of the basement and the construction of a shelter. The total cost of the work was 2.3 million hryvnias.

In August, 379,600 hryvnias were transferred to the contractor, and in November—another 1.94 million hryvnias. Investigators link potential violations specifically to the second payment. According to law enforcement officials, false information was included in Certificate of Completion No. 2, resulting in the amount being overstated by more than 318,000 hryvnias. Specifically, the cost of metal handrails, according to the investigation, was overstated by 90,500 hryvnias.

Read about the judge’s ruling regarding the contractor on the Center for Public Investigations website.

Law enforcement officials also claim that an additional 9,100 hryvnias was overcharged in the payments for faucets. The largest amount—218,900 hryvnias—relates to a site hoist. In the documents, it was valued at 260,500 hryvnias, while the final resource statement listed 246,000 hryvnias. Investigators also pointed out that the specifications of the installed equipment did not match those in the design and cost estimate documentation.

After the act was signed, the entire amount was transferred to the contractor. Investigators believe that as a result, the Odesa community may have suffered losses of over 318,000 hryvnias. The prosecutor requested that the suspect be placed under personal recognizance. 

Additionally, in Odesa, six years after the renovation of a sports complex, there are suspicions of embezzlement. Investigators are gathering documents to determine whether budget funds were indeed used for their intended purpose and whether the work performed corresponds to what the state paid for. 

 

Анна Літман

You may also like:

Sept. 5, 2026

The Cabinet of Ministers has changed the rules for agricultural exports due to Russian aggression in the Black Sea region

The winners and recipients of the Golden Duke were announced at the 17th Odessa Film Festival

Construction of an agricultural park costing 884 million hryvnias has been approved in the Odesa region

An additional 100 million has been allocated for the repair of 10 kilometers of road in the Mykolaiv region

A grain warehouse in the Odesa region has been put up for sale for $650,000

This fall, Lviv plans to transfer some of its trolleybuses to Odesa

In Odessa, the PORT literary festival brought together writers and readers

Odessa has spent a quarter of its development budget in eight months

Odessa Has Outlined Steps for the Construction of a Waste Recycling Complex

Global food prices have skyrocketed due to attacks on ports in the Odesa region

In Chornomorsk, the water utility announced its intention to raise water rates

In the Odesa region, school cafeterias will be addressed following complaints from parents

The daughter of Saldo, the so-called head of the Kherson region, has been accused of crimes against national security

Trams and trolleybuses have returned to the streets of Odessa on a limited basis

NABU conducted searches at the home of Kipper, head of the Odesa Regional State Administration