In Mykolaiv, a company was demanded to pay 2 million for an unfinished shelter

(Lyceum 38. PHOTOS: From the lyceum's website)

The prosecutor's office initiated legal action to recover damages and penalties from Master Bud-Montazh LLC. The contractor, registered in Mykolaiv, failed to fulfill its contractual obligations to reconstruct a school shelter worth almost UAH 20 million in time.

According to the Mykolaiv District Prosecutor's Office, the issue is the reconstruction of the basement of Lyceum No. 38 named after Volodymyr Chaika, where the shelter was to be arranged.

Despite the fact that the company was registered in 2020 with an authorized capital of only two thousand hryvnias, it received a large-scale contract that it ultimately failed to fulfill on time.

Investigative actions revealed that under the leadership of director Dmytro Chepak, the company probably overstated the scope and cost of the work performed, which caused budget losses of more than UAH 2.8 million. In addition, law enforcement officers recorded facts of overpayment for technical supervision services. Although the facility was supposed to be commissioned in February 2025, the contractor and the customer illegally extended the construction period by 10 months through four additional agreements.

The prosecutor's office emphasizes that the capital construction department of the Mykolaiv City Council ignored its right to collect fines for late payment, which led to the current lack of readiness of the protective structure. In parallel with this case, the activities of Master Bud-Montazh LLC are being investigated in the framework of criminal proceedings under the article on misappropriation and embezzlement of property through abuse of office.

The police are investigating possible fraud not only at the Lyceum No. 38 facility, but also during the renovation of the dormitory building of the Mykolaiv Professional College of Physical Education. The company's accounts are currently blocked to ensure compensation for the damage caused to the community.

Катерина Глушко

You may also like:

July 26, 2026

In Mykolaiv, 5.2 million was allocated for the renovation of the intensive care unit

A water utility in the Mykolaiv region rejected lower bids and selected a contractor for 16 million

In Mykolaiv, officials approved the transfer of land along the Odesa–Melitopol–Novoazovsk highway to the state

Two civilian vessels were damaged in an attack in the Mykolaiv region

July 25, 2026

Why Logistics Is Key to the Success of Combat Operations Advertisement

A Conscious Choice: How to Find Your Place on the Front Lines or Behind the Lines Advertisement

A saboteur from Mykolaiv avoided prison for setting fire to Ukrzaliznytsia facilities

July 24, 2026

Allies of the new interior minister from the Mykolaiv region received apartments and promotions despite the scandals

"A child needs adults who will be there for the long haul": How the Ostapchuks from Mykolaiv became parents to nine children Advertisement

Features of the Range Rover Sport for drivers who appreciate dynamic performance and cutting-edge technology Advertisement

Mykolaiv lacks funds for water and sewer services for housing for internally displaced persons

July 23, 2026

In the Mykolaiv region, a company owned by a lawmaker was awarded a road construction contract worth 800 million

Budget fraud totaling 52 million was uncovered in the Odesa region

Sign language interpretation is planned for sessions of the Mykolaiv City Council

A former judge from the Mykolaiv region reported assets worth millions in his final financial disclosure statement